Details Make the Job, Inside and Out

As we make the final push to finish the US Steel Realty office, we are striving to complete the job with excellence.

 

 

 

 

 

 

 

 

 

 

Details make the job. This week, those aesthetics include brick work on the parking lot, interior paint, crown molding and ceramic tile. We are also pleased to say that safety has remanded top of mind. A steel stair rail and electrical meters for permanent power were both successfully installed.

We estimate an on-time completion, just after the new year.

Artist’s Vision is Close to Reality

The US Steel Realty building is looking more like it’s artist rendering. Paint has begun on the veranda side.

Brick work continues to progress at the gables and entrance arches.

As well as our electrical service area in place.

Drywall and finishes are progressing here on the second floor, and in the basement also.